Cannabis Cultivation Facility Power Planning: The Bartlett Unit 16 Case Study Khushboo Thakkar October 26, 2026

Cannabis Cultivation Facility Power Planning: The Bartlett Unit 16 Case Study

Case Studies · Facility Design · California — By DRM · October 2026 · 9 min read

Project snapshot: Bartlett Avenue, Unit 16 · Adelanto, California · 30,000+ sq ft two-tier cultivation · Owner: Pot West · Project lead: Critical Climates · DRM role: outside consultant.

Table of contents

Overview

Many conversations about cannabis cultivation facility design focus on the canopy: lighting, HVAC, fertigation and room layout. Far fewer focus on the one thing those systems depend on, which is whether the building has the power to run them.

At Bartlett Avenue Unit 16 in Adelanto, California, that question was answered the hard way. A 30,000+ square foot, two-tier cultivation build-out had been designed around 2,500 amps of utility service. When the system was energized, the building had 1,200. This was a Critical Climates project, delivered for the building’s owner, Pot West. DRM was brought in as an additional, outside consultant to provide guidance and feedback on how to address the problems that arose in the field.

This case study covers what went wrong, how real-world load data and as-built documentation helped diagnose it, the guidance DRM provided, how power from adjacent units closed the gap, and what any operator planning a new facility should take from it.

DRM’s role on this project: Critical Climates led the Bartlett Unit 16 project. DRM served strictly in a consulting capacity, providing guidance, feedback and recommendations to Critical Climates and the owner. Design, engineering and implementation decisions remained with Critical Climates and their project team.

Watch the Video

Watch Nic Bucholz walk through the Bartlett Unit 16 power shortfall (22 minutes).

Why Power Planning Can’t Wait for Construction

Pot West had acquired multiple buildings across several cities, and Unit 16 was designed as a full commercial cultivation build-out. The electrical design assumed Southern California Edison would deliver a 2,500-amp service. That assumption shaped everything downstream: panel schedules, lighting circuits, HVAC sizing and the operating schedule itself.

SCE installed a 1,200-amp service instead of the 2,500 amps the design assumed. Visually, the installation looked a lot like a 2,500-amp service, so the owner believed the power was already in place. It wasn’t, and a utility upgrade was years away.

The operating plan raised the stakes further. The owner wanted to run two tiers of canopy across 30,000+ square feet on a standard 24-hour schedule, not a staggered “flip” schedule. A flip schedule offsets light cycles between rooms, so the full lighting load never runs at once, and it is the usual answer when power is limited. Here, it was off the table.

Design factorOriginal planField realityWhy it matters
Utility service2,500A1,200A installedLess than half the capacity the build-out was designed around
Utility upgrade timelineAssumed availableYears awayNo near-term fix from the utility
CanopyTwo-tier, 30,000+ sq ftUnchangedLighting and HVAC loads scale with every tier added
Light scheduleStandard 24-hour (no flip)Standard 24-hour (owner requirement)Removes the most common way to manage limited power

When the Lights Came On: Discovering the Shortfall

The capacity problem didn’t show up on paper. It showed up the moment the system was energized. No one had verified whether the transformer serving the building was actually large enough for the load it was designed to carry.

Lighting made the gap considerably worse. The original design used a conventional lighting package. The fixtures that were ultimately installed drew far more power, and that change rippled through the entire electrical design.

Lighting elementDesign basisInstalledWhy it matters
Overhead fixtures800–900W conventional fixtureHigher-wattage fixtureOverhead lights are the single largest load in a flower room
Under-canopy lightingTwo 120W fixtures220W fixturesUnder-canopy load multiplies quickly across a two-tier canopy
Total lighting loadPer designAn estimated 30–50% higher (DRM’s estimate from the installed fixture schedule)Exceeded what the building was designed for, before any HVAC or support loads

“The moment they energized the system, they found that they didn’t have enough capacity, because no one thought to look at whether or not the transformer was actually big enough.”

— Nic Bucholz, CEO

Measuring Real-World Load: The 77-Hour Study

When a facility is this close to its limits, calculations alone aren’t enough. Our standing recommendation to clients in this position is to invest a few thousand dollars in a hardwired, live-feed data logger connected to the main line. It shows exactly when loads come on and off, how close the facility is to maximum capacity, and, when it hits capacity, for how long. That is the information needed to avoid overloading the system.

At Unit 16, the electrical subcontractor ran a 77-hour load study. The data made two things clear.

Load typeWhat it representsWhat Unit 16 showed
Theoretical loadWhat the code book and calculations say the building should drawHigher than real-world demand, as is often the case
Measured loadWhat the facility actually draws in operationStill more than the 1,200A service could carry

The second finding was the critical one. Running a back-to-back schedule with no overnight cruise period, the facility was hitting peak capacity multiple times. Left unaddressed, that leads to tripped breakers, burned circuits and, at worst, a transformer that fails because it simply cannot withstand the load.

“The theoretical load is always considerably higher than the real-world load. The irony, though, is that even though there’s this differential, what they installed exceeded the capacity of the real world.”

— Nic Bucholz, CEO

Field Conditions vs. Drawings: Why As-Builts Mattered

A second problem surfaced alongside the capacity shortfall: what had been installed wasn’t what was on the plans. Before reliable guidance could be given, the drawings had to be compared against field conditions to identify what had been built.

On most projects, the contractor produces as-built documents during construction to record how the facility was really put together. Updated red-line as-builts show exactly how every system is laid out, which makes it far easier to see why problems are occurring. A design produced at a desk cannot account for conditions it doesn’t know exist.

With accurate as-builts on hand, DRM could give Critical Climates and the owner well-grounded guidance across multiple meetings. Every recommendation was grounded in the building as it stood, not the building as it was drawn.

The Solution: Integrating Power from Adjacent Units

With a utility upgrade years out and a flip schedule ruled out, Critical Climates and the project team brought in capacity from the neighboring suites, with DRM providing consulting guidance on the approach. Power was pulled from Units 13 and 15, roughly 600 amps from one and 800 amps from the other. Combined with the existing service, that brought Unit 16 back to roughly the level its original design called for.

How the new power was tied in mattered as much as how much was added. Splitting a room’s load across separate sources creates operational and safety risks. The added feeds had to be integrated correctly with the main feed serving the rest of the facility so the building would operate as one coordinated system.

The result: the owner got the operation they asked for, a full two-tier facility running on a standard 24-hour schedule, without waiting years on the utility.

“In this industry, you can build trust and develop a stronger skill set by giving the client what they’re asking for, rather than just telling them you can’t do it because it’s the path of least resistance. It will challenge you in ways you didn’t know were possible, so that for the next project, you have that answer readily available.”

— Nic Bucholz, CEO

A Power-Planning Roadmap for Cultivation Facilities

Looking back, much of the difficulty at Unit 16 could have been avoided earlier. From our perspective as consultants, the biggest difference on a fresh start would be a heavy focus on the power upgrade from day one. These are the steps we recommend to any operator planning a cultivation facility:

  • Verify the installed utility service. Confirm the actual transformer and service size, not what was promised or what the equipment appears to be.
  • Match the operating schedule to available power. If the business model allows a flip schedule, it is the simplest way to manage limited capacity. If it requires 24-hour operation, design for that from the start.
  • Pre-plan power from adjacent suites. In multi-unit buildings, plan the integration of neighboring capacity early rather than retrofitting it under pressure.
  • Lock in lighting selections before the electrical design is finalized. Fixture wattage drives the electrical design. A late switch to higher-wattage overhead or under-canopy fixtures can add an estimated 30–50% to lighting load.
  • Install a live-feed data logger. For a few thousand dollars, a hardwired logger on the main line shows how close to capacity the facility runs, and for how long.
  • Keep as-builts current. Update red lines as field conditions change so every decision rests on how the building was built.
  • Be clear about real limitations. When several units share a power supply, sending most of it to one unit leaves less for the others. Owners need to know that before they commit to an operating plan.

Work With DRM on Your Cultivation Facility

DRM designs, reviews and manages commercial cannabis facilities using real-world operating experience, not just the code book. Whether you are planning a new build-out or solving a capacity problem in a facility that’s already under construction, our team can help you find an answer that supports the operation you want to run. A design audit checks power, lighting and equipment assumptions before construction starts, and a facility assessment diagnoses capacity problems in a building that is already built or under construction.

Contact our team to plan a cannabis facility around the power you actually have.

Let’s work together →

Bartlett Unit 16 Case Study FAQs

What was the main challenge at Bartlett Unit 16?

The facility was designed around a 2,500-amp utility service, but only 1,200 amps were installed, and a utility upgrade was years away.

What was DRM’s role at Bartlett Unit 16?

DRM was an outside consultant only. The project belonged to Critical Climates, which led the work for the owner, Pot West. DRM provided guidance, feedback and recommendations; it was not responsible for the project’s design, engineering or construction.

When was the power shortfall discovered?

When the system was energized during construction. The installed service looked like a 2,500-amp installation, so the shortfall wasn’t obvious beforehand.

How did lighting affect the electrical design?

The installed overhead and under-canopy fixtures drew considerably more power than the conventional fixtures in the original design, adding an estimated 30–50% to the lighting load.

What is the difference between theoretical load and measured load?

Theoretical load is what code and calculations say a building should draw. Measured load is what it draws in operation. Theoretical load is usually higher, but at Unit 16, even the measured load exceeded the available service.

Why not switch to a flip schedule?

A flip schedule is the most common way to manage limited power, but the owner required a standard 24-hour operation. The solution had to work within that requirement.

How was the problem solved?

Critical Climates and the project team brought in power from adjacent Units 13 and 15 and integrated it with the facility’s main feed, restoring capacity close to the original design. DRM advised throughout as a consultant.

What is the most important lesson for new cultivation facilities?

Verify your power before you design around it, and lock in equipment selections, especially lighting, before the electrical design is finalized.

Disclaimer: This case study is provided for informational purposes only and does not constitute legal, engineering, architectural or construction advice. Every facility has unique conditions; consult qualified professionals before making design or construction decisions.